This dataset contains capital commitment plan data by project type, budget line and source of funds. The dollar values are in thousands. The dataset is updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans.

ELECTRICAL CONDUIT REPLACEMENT (SANDY) ()

Details

Publication Date 
Summary Original Current Change (#)
Budget
Start
End
Duration
Borough
Managed By
Project Type
10-year Plan Category
Budget Lines
Community Districts Served
Explanation for Delay
Scope Summary
Site Description
City Prior Spending
Non City Prior Spending

* All numbers are in the chart are thousands.

Next 5 Years of Spending

* All numbers are in the chart are thousands.

Prior Spending

* All numbers are in the chart are thousands.

Budget Over Time

Additional Project Information

Description Total City Planned Commit Max Date Min Date Managing Agency Name

Commitments

Description Date Commitment Description Commitment Type Total Planned Commit

  Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.

Suggest a Change

Change Log

  • 05/24/2023
    • Current Budget increase ▲ $2.62M
  • 03/09/2022
    • Original Start postponed ▲ 6.9 years
    • Current Start postponed ▲ 3.0 years
    • Original End postponed ▲ 5.0 years
    • Current End anticipated ▼ 2.0 years
  • 01/14/2021
    • Original Budget decrease ▼ $15.7M
    • Current Budget increase ▲ $7.80M
  • 11/23/2020
    • Original Budget increase ▲ $15.7M
    • Current Budget decrease ▼ $7.80M
    • CONSTRUCTION TO 75% Original anticipated ▼ 3.1 months
    • CONSTRUCTION TO 75% Current anticipated ▼ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 3.0 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 6.1 months
    • SUBSTANTIAL COMPLETION Current anticipated ▼ 6.1 months
    • PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 6.1 months
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 6.1 months
  • 04/16/2020
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 6.1 months
    • SUBSTANTIAL COMPLETION Current anticipated ▼ 6.1 months
    • CONSTRUCTION TO 75% Original anticipated ▼ 3.1 months
    • CONSTRUCTION TO 75% Current anticipated ▼ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 3.0 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
    • PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 6.1 months
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 6.1 months
  • 01/16/2020
    • Original Budget decrease ▼ $15.7M
    • Current Budget increase ▲ $7.80M
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 3.0 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
    • PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 6.1 months
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 6.1 months
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 6.1 months
    • SUBSTANTIAL COMPLETION Current anticipated ▼ 6.1 months
    • CONSTRUCTION TO 75% Original anticipated ▼ 3.1 months
    • CONSTRUCTION TO 75% Current anticipated ▼ 3.1 months
  • 10/25/2019
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 3.0 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
    • PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 6.1 months
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 6.1 months
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 6.1 months
    • SUBSTANTIAL COMPLETION Current anticipated ▼ 6.1 months
    • CONSTRUCTION TO 75% Original anticipated ▼ 3.1 months
    • CONSTRUCTION TO 75% Current anticipated ▼ 3.1 months
  • 04/25/2019
    • Original Budget increase ▲ $15.7M
    • Current Budget decrease ▼ $8.01M
    • CONSTRUCTION TO 75% Original anticipated ▼ 3.1 months
    • CONSTRUCTION TO 75% Current anticipated ▼ 3.1 months
    • PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 6.1 months
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 6.1 months
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 6.1 months
    • SUBSTANTIAL COMPLETION Current anticipated ▼ 6.1 months
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 3.0 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
  • 12/2/2021
    • Current Budget increase ▲ $207K
    • Original Start anticipated ▼ 52.0 years
    • Current Start anticipated ▼ 52.0 years
    • Original End anticipated ▼ 52.9 years
    • Current End anticipated ▼ 52.9 years
    • CONSTRUCTION TO 75% Original postponed ▲ 3.1 months
    • CONSTRUCTION TO 75% Current postponed ▲ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Original postponed ▲ 3.0 months
    • BID AWARD AND REGISTER CONTRCT Current postponed ▲ 2.0 months
    • PUNCHLIST COMPLETE, JOB CLOSED Original postponed ▲ 6.1 months
    • PUNCHLIST COMPLETE, JOB CLOSED Current postponed ▲ 6.1 months
    • SUBSTANTIAL COMPLETION Original postponed ▲ 6.1 months
    • SUBSTANTIAL COMPLETION Current postponed ▲ 6.1 months