This dataset contains capital commitment plan data by project type, budget line and source of funds. The dollar values are in thousands. The dataset is updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans.

CITY HALL STEPS RECONSTRUCTION

Publication Date 
Summary Original Current Change (#)
Budget
Start
End
Duration
Project ID
Borough
Managed By
10-year Plan Category
Budget Lines
Community Districts Served
Explanation for Delay
Scope Summary
Site Description

Timeline

Phase Original Current Change

Suggest a Change

Change Log

  • 03/09/2022
    • Original Start postponed ▲ 1.6 years
    • Current Start postponed ▲ 1.6 years
    • Original End anticipated ▼ 2.2 years
    • Current End anticipated ▼ 2.2 years
  • 08/05/2021
    • Current Budget decrease ▼ $3.94M
  • 11/23/2020
    • Current Budget decrease ▼ $100K
  • 04/16/2020
    • Current Budget decrease ▼ $288K
  • 01/16/2020
    • Current Budget decrease ▼ $251K
  • 10/25/2019
    • Current Budget decrease ▼ $1.65M
  • 04/25/2019
    • Current Budget decrease ▼ $305K
  • 12/2/2021
    • Current Budget increase ▲ $6.33M
    • Original Start anticipated ▼ 52.0 years
    • Current Start anticipated ▼ 52.0 years
    • Original End anticipated ▼ 52.9 years
    • Current End anticipated ▼ 52.9 years

This data comes from Capital Project Detail Data - DollarsLast updated 09/28/2022