Project ID
MA Project ID
Category
Type
Hoover Playground Q220G-121M
Current Phase
Phase Start
Phase End
Min Date
Max Date
Managing Agency
Sponsor Agency
Budget Lines
Type Category
CCP Version
Forecasts
Summary | Original | Current | Change (#) |
---|---|---|---|
Budget | |||
Project Completion | |||
Duration |
Agency Project Schedule
Project Schedule History
Period | Current Phase | Completion Date Forecast | Variance (day) | Reason for Forecast Completion Change | Managing Agency Name | Data as of |
---|
Budget & Spending
Planned
Adopted
Allocated
Commited
Spent
Checkbook
History
Year-Month Reported | Total Budget | Budget Variance | Budget Variance % | Spend to Date | Spend to Date % |
---|
Funding Source
Fiscal Year | Total Budget (City + Non City) | City | Non City | Spend |
---|
Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.
Change Log
-
09/2023
- Current Budget increase ▲ $70.0K
- Current End anticipated ▼ 7.1 months
- Current Duration decrease ▼ 7.1 months
-
05/2024
- Current End postponed ▲ 1.1 years
- Current Duration increase ▲ 1.1 years
-
09/2024
- Current Budget increase ▲ $164K
- Current End postponed ▲ 2.1 months
- Current Duration increase ▲ 2.1 months
-
01/2025
- Current End postponed ▲ 4.8 months
- Current Duration increase ▲ 4.8 months
Commitments
Description | Date | Commitment Description | Commitment Type | Total Planned Commit |
---|