This dataset contains capital commitment plan data by project type, budget line and source of funds. The dollar values are in thousands. The dataset is updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans.
Capital Project Detail Data - Dollars
Green Thumb Irrigation systems (Brooklyn) ()
Details
Publication Date
Summary | Original | Current | Change (#) |
---|---|---|---|
Budget | |||
Start | |||
End | |||
Duration |
Borough | |
---|---|
Managed By | |
Project Type | |
10-year Plan Category | |
Budget Lines | |
Community Districts Served | |
Explanation for Delay | |
Scope Summary | |
Site Description | |
City Prior Spending | |
Non City Prior Spending |
Milestones
* All numbers are in the chart are thousands.
Next 5 Years of Spending
* All numbers are in the chart are thousands.
Prior Spending
* All numbers are in the chart are thousands.
Budget Over Time
Additional Project Information
Description | Total City Planned Commit | Max Date | Min Date | Managing Agency Name |
---|
Commitments
Description | Date | Commitment Description | Commitment Type | Total Planned Commit |
---|
Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.
Change Log
-
05/24/2023
- Current Budget decrease ▼ $50.0K
- DEVELOP SCOPE Original anticipated ▼ 4.2 years
- DEVELOP SCOPE Current anticipated ▼ 4.8 years
- DESIGN Original anticipated ▼ 4.8 years
- DESIGN Current anticipated ▼ 3.3 years
- BID/ REGISTER CONTRACT Original anticipated ▼ 4.8 years
- BID/ REGISTER CONTRACT Current anticipated ▼ 2.5 years
- CONSTRUCTION Original anticipated ▼ 5.2 years
- CONSTRUCTION Current anticipated ▼ 12.2 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 5.2 years
-
02/10/2023
- DEVELOP SCOPE Original anticipated ▼ 4.2 years
- DEVELOP SCOPE Current anticipated ▼ 4.8 years
- DESIGN Original anticipated ▼ 4.8 years
- DESIGN Current anticipated ▼ 3.3 years
- BID/ REGISTER CONTRACT Original anticipated ▼ 4.8 years
- BID/ REGISTER CONTRACT Current anticipated ▼ 2.5 years
- CONSTRUCTION Original anticipated ▼ 5.2 years
- CONSTRUCTION Current anticipated ▼ 12.2 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 5.2 years
-
10/12/2022
- DEVELOP SCOPE Original anticipated ▼ 4.2 years
- DEVELOP SCOPE Current anticipated ▼ 4.8 years
- DESIGN Original anticipated ▼ 4.8 years
- DESIGN Current anticipated ▼ 3.3 years
- BID/ REGISTER CONTRACT Original anticipated ▼ 4.8 years
- BID/ REGISTER CONTRACT Current anticipated ▼ 2.5 years
- CONSTRUCTION Original anticipated ▼ 5.2 years
- CONSTRUCTION Current anticipated ▼ 12.2 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 5.2 years
-
05/17/2022
- Current Budget decrease ▼ $495K
- PUNCHLIST COMPLETE, JOB CLOSED Original postponed ▲ 5.2 years
- DEVELOP SCOPE Original anticipated ▼ 4.2 years
- DEVELOP SCOPE Current anticipated ▼ 4.8 years
- DESIGN Original anticipated ▼ 4.8 years
- DESIGN Current anticipated ▼ 3.3 years
- BID/ REGISTER CONTRACT Original anticipated ▼ 4.8 years
- BID/ REGISTER CONTRACT Current anticipated ▼ 2.5 years
- CONSTRUCTION Original anticipated ▼ 5.2 years
- CONSTRUCTION Current anticipated ▼ 12.2 months
-
03/09/2022
- Original Start postponed ▲ 8.1 months
- Current Start postponed ▲ 8.1 months
- Original End anticipated ▼ 8.0 years
- Current End anticipated ▼ 3.8 years
- DEVELOP SCOPE Original anticipated ▼ 4.2 years
- DEVELOP SCOPE Current anticipated ▼ 4.8 years
- DESIGN Original anticipated ▼ 4.8 years
- DESIGN Current anticipated ▼ 3.3 years
- BID/ REGISTER CONTRACT Original anticipated ▼ 4.8 years
- BID/ REGISTER CONTRACT Current anticipated ▼ 2.5 years
- CONSTRUCTION Original anticipated ▼ 5.2 years
- CONSTRUCTION Current anticipated ▼ 12.2 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 5.2 years
-
12/02/2021
- Current Budget decrease ▼ $300K
- Original Start anticipated ▼ 52.2 years
- Current Start anticipated ▼ 52.2 years
- Original End anticipated ▼ 52.9 years
- Current End anticipated ▼ 52.9 years
- DEVELOP SCOPE Original postponed ▲ 9.2 months
- DEVELOP SCOPE Current postponed ▲ 3.0 months
- DESIGN Original postponed ▲ 3.0 months
- DESIGN Current anticipated ▼ 3.1 months
- BID/ REGISTER CONTRACT Original postponed ▲ 3.1 months
- BID/ REGISTER CONTRACT Current anticipated ▼ 6.1 months
- CONSTRUCTION Original anticipated ▼ 3.0 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 3.0 months