This dataset contains capital commitment plan data by project type, budget line and source of funds. The dollar values are in thousands. The dataset is updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans.
Capital Project Detail Data - Dollars
WASHINGTON AVENUE SAFETY IMPROVEMENTS ()
Details
Publication Date
Summary | Original | Current | Change (#) |
---|---|---|---|
Budget | |||
Start | |||
End | |||
Duration |
Borough | |
---|---|
Managed By | |
Project Type | |
10-year Plan Category | |
Budget Lines | |
Community Districts Served | |
Explanation for Delay | |
Scope Summary | |
Site Description | |
City Prior Spending | |
Non City Prior Spending |
Milestones
* All numbers are in the chart are thousands.
Next 5 Years of Spending
* All numbers are in the chart are thousands.
Prior Spending
* All numbers are in the chart are thousands.
Budget Over Time
Additional Project Information
Description | Total City Planned Commit | Max Date | Min Date | Managing Agency Name |
---|
Commitments
Description | Date | Commitment Description | Commitment Type | Total Planned Commit |
---|
Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.
Change Log
-
02/10/2023
- Current Start anticipated ▼ 20.2 years
- Current End postponed ▲ 6.0 months
-
10/12/2022
- Current Start postponed ▲ 20.2 years
- Current End anticipated ▼ 5.9 years
- PRELIMINARY DESIGN Original anticipated ▼ 2.2 years
- PRELIMINARY DESIGN Current anticipated ▼ 3.6 years
- CONSTRUCTION TO 25% Original anticipated ▼ 1.2 years
- CONSTRUCTION TO 25% Current anticipated ▼ 4.6 years
- BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 1.5 years
- BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 4.2 years
- FINAL DESIGN Original anticipated ▼ 1.8 years
- FINAL DESIGN Current anticipated ▼ 4.0 years
- DEVELOP SCOPE Original anticipated ▼ 2.6 years
- DEVELOP SCOPE Current anticipated ▼ 3.2 years
- CONSTRUCTION COMPLETION Current anticipated ▼ 30.4 years
- CONSTRUCTION TO 50% Original postponed ▲ 10.1 months
- CONSTRUCTION TO 50% Current postponed ▲ 4.9 years
- CONSTRUCTION TO 75% Original postponed ▲ 6.1 months
- CONSTRUCTION TO 75% Current postponed ▲ 5.2 years
- SUBSTANTIAL COMPLETION Original postponed ▲ 1.0 months
- SUBSTANTIAL COMPLETION Current postponed ▲ 5.7 years
- PUNCHLIST COMPLETE, JOB CLOSED Current postponed ▲ 8.0 years
- PROJECT START Current postponed ▲ 32.1 years
- DESIGN START Current postponed ▲ 32.1 years
- DESIGN COMPLETION Current postponed ▲ 32.1 years
- CONSTRUCTION START Current postponed ▲ 32.1 years
- ORIGINAL EQUIP & FURNISHING Original postponed ▲ 3.0 months
- ORIGINAL EQUIP & FURNISHING Current postponed ▲ 5.5 years
-
05/17/2022
- Current Budget decrease ▼ $700K
- Current End anticipated ▼ 3.1 years
-
03/09/2022
- Original Start postponed ▲ 1.9 years
- Current Start postponed ▲ 1.9 years
- Current End anticipated ▼ 1.6 years
-
12/02/2021
- Current Budget decrease ▼ $285K
- Original Start anticipated ▼ 52.1 years
- Current Start anticipated ▼ 52.1 years
- Original End anticipated ▼ 52.9 years
- Current End anticipated ▼ 52.8 years
-
08/05/2021
- Original Start postponed ▲ 52.1 years
- Current Start postponed ▲ 52.1 years
- Original End postponed ▲ 52.9 years
- Current End postponed ▲ 52.9 years
-
04/16/2020
- Current Budget decrease ▼ $280K
-
10/25/2019
- Current Budget decrease ▼ $1.00K
-
04/25/2019
- Current Budget decrease ▼ $49.0K