8th Avenue Sunset Park Chinatown Archway ()
Details
Publication Date
Summary | Original | Current | Change (#) |
---|---|---|---|
Budget | |||
Start | |||
End | |||
Duration |
Borough | |
---|---|
Managed By | |
Project Type | |
10-year Plan Category | |
Budget Lines | |
Community Districts Served | |
Explanation for Delay | |
Scope Summary | |
Site Description | |
City Prior Spending | |
Non City Prior Spending |
Milestones
* All numbers are in the chart are thousands.
Next 5 Years of Spending
* All numbers are in the chart are thousands.
Prior Spending
* All numbers are in the chart are thousands.
Budget Over Time
Additional Project Information
Description | Total City Planned Commit | Max Date | Min Date | Managing Agency Name |
---|
Commitments
Description | Date | Commitment Description | Commitment Type | Total Planned Commit |
---|
Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.
Change Log
-
03/09/2022
- Original Start postponed ▲ 5.8 years
- Current Start anticipated ▼ 2.2 years
- Original End postponed ▲ 2.5 years
- Current End anticipated ▼ 6.5 years
-
12/02/2021
- Original Start anticipated ▼ 52.2 years
- Current Start anticipated ▼ 52.2 years
- Original End anticipated ▼ 52.7 years
- Current End anticipated ▼ 52.7 years
-
08/05/2021
- Original Start postponed ▲ 52.2 years
- Current Start postponed ▲ 52.2 years
- Original End postponed ▲ 52.7 years
- Current End postponed ▲ 52.7 years
-
11/23/2020
- Current Budget decrease ▼ $3.97M
-
10/25/2019
- Current Budget decrease ▼ $0
-
04/25/2019
- Current Budget decrease ▼ $0