FT. WASHINGTON ARMORY - BOILER UPGRADE

Current Phase
Phase Start
Phase End
Min Date
Max Date
Managing Agency
Sponsor Agency
Budget Lines
Type Category
CCP Version

Forecasts

Summary Original Current Change (#)
Budget
Project Completion
Duration

Agency Project Schedule

Project Schedule History

Period Current Phase Completion Date Forecast Variance (day) Reason for Forecast Completion Change Managing Agency Name Data as of

Budget & Spending

Planned
Adopted
Allocated
Commited
Spent
Checkbook

History

Year-Month Reported Total Budget Budget Variance Budget Variance % Spend to Date Spend to Date %

Funding Source

Fiscal Year Total Budget (City + Non City) City Non City Spend

  Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.

Suggest a Change

Change Log

  • 09/2023
    • Current Budget decrease ▼ $456
  • 01/2024
    • Current Budget increase ▲ $3.00M
  • 05/2024
    • Current Budget decrease ▼ $1.15M
    • Current End postponed ▲ 10.2 months
    • Current Duration increase ▲ 10.2 months
  • 09/2024
    • Current Budget increase ▲ $1.00M
  • 01/2025
    • Current End postponed ▲ 1.7 years
    • Current Duration increase ▲ 1.7 years

Commitments

Description Date Commitment Description Commitment Type Total Planned Commit