Capital Project Detail Data - Dollars
WEST TREMONT AVENUE OVER METRO NORTH RR BIN:2241460 ()
Details
Publication Date
Summary | Original | Current | Change (#) |
---|---|---|---|
Budget | |||
Start | |||
End | |||
Duration |
Borough | |
---|---|
Managed By | |
Project Type | |
10-year Plan Category | |
Budget Lines | |
Community Districts Served | |
Explanation for Delay | |
Scope Summary | |
Site Description | |
City Prior Spending | |
Non City Prior Spending |
Milestones
* All numbers are in the chart are thousands.
Next 5 Years of Spending
* All numbers are in the chart are thousands.
Prior Spending
* All numbers are in the chart are thousands.
Budget Over Time
Additional Project Information
Description | Total City Planned Commit | Max Date | Min Date | Managing Agency Name |
---|
Commitments
Description | Date | Commitment Description | Commitment Type | Total Planned Commit |
---|
Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.
Change Log
-
05/24/2023
- Current Budget decrease ▼ $432K
- CONSTRUCTION START Current postponed ▲ 5.2 years
-
02/10/2023
- Current Budget decrease ▼ $25.0M
- CONSTRUCTION START Current postponed ▲ 5.2 years
-
10/12/2022
- CONSTRUCTION START Current postponed ▲ 5.2 years
-
05/17/2022
- Current Budget decrease ▼ $419K
- CONSTRUCTION START Current anticipated ▼ 5.2 years
-
03/09/2022
- Current Budget decrease ▼ $5.10M
- Original Start postponed ▲ 7.0 years
- Current End anticipated ▼ 3.9 years
- CONSTRUCTION START Current postponed ▲ 5.2 years
-
12/02/2021
- Current Budget decrease ▼ $1.32M
- Original Start anticipated ▼ 52.4 years
- Original End anticipated ▼ 52.4 years
- Current End anticipated ▼ 52.4 years
- CONSTRUCTION START Current postponed ▲ 3.0 months
-
08/05/2021
- Current Budget increase ▲ $160K
- Original Start postponed ▲ 52.4 years
- Original End postponed ▲ 52.4 years
- Current End postponed ▲ 52.4 years
-
01/14/2021
- Current Budget decrease ▼ $3.73M
- Current Start anticipated ▼ 70.1 years
- CONSTRUCTION START Current postponed ▲ 3.0 months
-
11/23/2020
- CONSTRUCTION START Current anticipated ▼ 3.0 months
-
04/16/2020
- Current Budget decrease ▼ $23.7M
- CONSTRUCTION START Current postponed ▲ 3.0 months
-
01/16/2020
- CONSTRUCTION START Current anticipated ▼ 3.0 months
-
10/25/2019
- Current Budget decrease ▼ $282K
- CONSTRUCTION START Current anticipated ▼ 3.0 months
-
04/25/2019
- Current Budget increase ▲ $1.00K