This dataset contains capital commitment plan data by project type, budget line and source of funds. The dollar values are in thousands. The dataset is updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans.

HOMELESS INITIATIVE

Publication Date 
Summary Original Current Change (#)
Budget
Start
End
Duration
Project ID
Borough
Managed By
10-year Plan Category
Budget Lines
Community Districts Served
Explanation for Delay
Scope Summary
Site Description

Timeline

Phase Original Current Change

Suggest a Change

Change Log

  • 03/09/2022
    • Original Start postponed ▲ 6.4 years
    • Current Start postponed ▲ 6.6 years
    • Original End postponed ▲ 4.5 years
    • Current End postponed ▲ 5.1 months
    • PUNCHLIST COMPLETE, JOB CLOSED Current postponed ▲ 2.6 years
  • 08/05/2021
    • Current Budget increase ▲ $39.0K
    • PUNCHLIST COMPLETE, JOB CLOSED Current postponed ▲ 5.1 months
  • 01/14/2021
    • PUNCHLIST COMPLETE, JOB CLOSED Current postponed ▲ 5.1 months
  • 11/23/2020
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 5.1 months
  • 04/16/2020
    • Current Budget decrease ▼ $1.36M
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 5.1 months
  • 01/16/2020
    • PUNCHLIST COMPLETE, JOB CLOSED Current postponed ▲ 5.1 months
  • 10/25/2019
    • Current Budget decrease ▼ $0
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 5.1 months
  • 04/25/2019
    • Current Budget increase ▲ $4.50M
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 5.1 months
  • 12/2/2021
    • Current Budget decrease ▼ $3.14M
    • Original Start anticipated ▼ 52.2 years
    • Current Start anticipated ▼ 52.3 years
    • Original End anticipated ▼ 52.6 years
    • Current End anticipated ▼ 52.8 years
    • PUNCHLIST COMPLETE, JOB CLOSED Current anticipated ▼ 5.1 months

This data comes from Capital Project Detail Data - DollarsLast updated 09/21/2022