This dataset contains capital commitment plan data by project type, budget line and source of funds. The dollar values are in thousands. The dataset is updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans.

Capital Project Detail Data - Dollars

REPLACEMENT OF ELECTRICAL AUTOMATIC TRANSFER SWITCHES ()

Details

Publication Date 
Summary Original Current Change (#)
Budget
Start
End
Duration
Borough
Managed By
Project Type
10-year Plan Category
Budget Lines
Community Districts Served
Explanation for Delay
Scope Summary
Site Description
City Prior Spending
Non City Prior Spending

* All numbers are in the chart are thousands.

Next 5 Years of Spending

* All numbers are in the chart are thousands.

Prior Spending

* All numbers are in the chart are thousands.

Budget Over Time

Additional Project Information

Description Total City Planned Commit Max Date Min Date Managing Agency Name

Commitments

Description Date Commitment Description Commitment Type Total Planned Commit

  Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.

Suggest a Change

Change Log

  • 05/24/2023
    • DESIGN Original anticipated ▼ 2.0 years
    • DESIGN Current anticipated ▼ 15.2 years
    • PUNCHLIST COMPLETE, JOB CLOSED Original postponed ▲ 4.0 years
    • SUBSTANTIAL COMPLETION Original postponed ▲ 3.9 years
    • BID AWARD AND REGISTER CONTRCT Original postponed ▲ 2.7 years
    • BID AWARD AND REGISTER CONTRCT Current postponed ▲ 14.2 years
  • 02/10/2023
    • PUNCHLIST COMPLETE, JOB CLOSED Original postponed ▲ 4.0 years
    • DESIGN Original anticipated ▼ 2.0 years
    • DESIGN Current anticipated ▼ 15.2 years
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 2.7 years
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 14.2 years
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 3.9 years
  • 10/12/2022
    • DESIGN Original anticipated ▼ 2.0 years
    • DESIGN Current anticipated ▼ 15.2 years
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 2.7 years
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 14.2 years
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 3.9 years
    • PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 4.0 years
  • 05/17/2022
    • Current Budget increase ▲ $2.12M
    • Current End anticipated ▼ 9.0 years
    • DESIGN Original anticipated ▼ 2.0 years
    • DESIGN Current anticipated ▼ 15.2 years
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 2.7 years
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 14.2 years
    • CONSTRUCTION TO 75% Original anticipated ▼ 3.9 years
    • CONSTRUCTION TO 75% Current anticipated ▼ 13.3 years
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 3.9 years
    • PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 4.0 years
  • 03/09/2022
    • Original Start postponed ▲ 5.8 years
    • Current Start postponed ▲ 6.7 years
    • Original End postponed ▲ 1.1 years
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 2.7 years
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 5.2 years
    • PUNCHLIST COMPLETE, JOB CLOSED Original postponed ▲ 4.0 years
    • SUBSTANTIAL COMPLETION Original postponed ▲ 3.9 years
    • DESIGN Original postponed ▲ 2.0 years
    • DESIGN Current postponed ▲ 6.2 years
  • 12/02/2021
    • Current Budget decrease ▼ $8.00K
    • Original Start anticipated ▼ 52.1 years
    • Current Start anticipated ▼ 52.2 years
    • Original End anticipated ▼ 52.7 years
    • Current End anticipated ▼ 52.5 years
    • DESIGN Current anticipated ▼ 2.0 months
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 1.0 months
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Current postponed ▲ 2.0 months
  • 08/05/2021
    • Original Start postponed ▲ 52.1 years
    • Current Start postponed ▲ 52.2 years
    • Original End postponed ▲ 52.7 years
    • Current End postponed ▲ 52.5 years
  • 01/14/2021
    • DESIGN Current anticipated ▼ 2.0 months
    • BID AWARD AND REGISTER CONTRCT Original postponed ▲ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
    • SUBSTANTIAL COMPLETION Original postponed ▲ 1.0 months
  • 11/23/2020
    • DESIGN Current anticipated ▼ 2.0 months
    • BID AWARD AND REGISTER CONTRCT Original postponed ▲ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
    • SUBSTANTIAL COMPLETION Original postponed ▲ 1.0 months
  • 04/16/2020
    • Current Budget decrease ▼ $1.03M
    • DESIGN Current postponed ▲ 2.0 months
    • BID AWARD AND REGISTER CONTRCT Original postponed ▲ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
    • SUBSTANTIAL COMPLETION Original postponed ▲ 1.0 months
  • 01/16/2020
    • DESIGN Current anticipated ▼ 2.0 months
    • SUBSTANTIAL COMPLETION Original anticipated ▼ 1.0 months
    • BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Current postponed ▲ 2.0 months
  • 10/25/2019
    • Current Budget decrease ▼ $0
    • DESIGN Current anticipated ▼ 2.0 months
    • BID AWARD AND REGISTER CONTRCT Original postponed ▲ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
    • SUBSTANTIAL COMPLETION Original postponed ▲ 1.0 months
  • 04/25/2019
    • Current Budget decrease ▼ $0
    • DESIGN Current anticipated ▼ 2.0 months
    • BID AWARD AND REGISTER CONTRCT Original postponed ▲ 3.1 months
    • BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 2.0 months
    • SUBSTANTIAL COMPLETION Original postponed ▲ 1.0 months