This dataset contains capital commitment plan data by project type, budget line and source of funds. The dollar values are in thousands. The dataset is updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans.
Capital Project Detail Data - Dollars
Water Main work in Brooklyn Waterfront Greenway, HWK1048E ()
Details
Publication Date
Summary | Original | Current | Change (#) |
---|---|---|---|
Budget | |||
Start | |||
End | |||
Duration |
Borough | |
---|---|
Managed By | |
Project Type | |
10-year Plan Category | |
Budget Lines | |
Community Districts Served | |
Explanation for Delay | |
Scope Summary | |
Site Description | |
City Prior Spending | |
Non City Prior Spending |
Milestones
* All numbers are in the chart are thousands.
Next 5 Years of Spending
* All numbers are in the chart are thousands.
Prior Spending
* All numbers are in the chart are thousands.
Budget Over Time
Additional Project Information
Description | Total City Planned Commit | Max Date | Min Date | Managing Agency Name |
---|
Commitments
Description | Date | Commitment Description | Commitment Type | Total Planned Commit |
---|
Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.
Change Log
-
05/24/2023
- Current Budget increase ▲ $49.0K
- DEVELOP SCOPE Original anticipated ▼ 3.3 years
- DEVELOP SCOPE Current anticipated ▼ 11.3 years
- PRELIMINARY DESIGN Original anticipated ▼ 4.0 years
- PRELIMINARY DESIGN Current anticipated ▼ 11.0 years
- FINAL DESIGN Original anticipated ▼ 4.9 years
- FINAL DESIGN Current anticipated ▼ 10.5 years
- BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 5.4 years
- BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 10.3 years
- CONSTRUCTION TO 25% Original anticipated ▼ 6.1 years
- CONSTRUCTION TO 25% Current anticipated ▼ 9.6 years
- CONSTRUCTION TO 50% Original anticipated ▼ 6.8 years
- CONSTRUCTION TO 50% Current anticipated ▼ 8.9 years
- CONSTRUCTION TO 75% Original anticipated ▼ 7.4 years
- CONSTRUCTION TO 75% Current anticipated ▼ 8.3 years
- ORIGINAL EQUIP & FURNISHING Original anticipated ▼ 7.9 years
- ORIGINAL EQUIP & FURNISHING Current anticipated ▼ 8.0 years
- SUBSTANTIAL COMPLETION Original anticipated ▼ 8.2 years
- SUBSTANTIAL COMPLETION Current anticipated ▼ 7.8 years
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 8.4 years
-
02/10/2023
- DEVELOP SCOPE Original anticipated ▼ 3.3 years
- DEVELOP SCOPE Current anticipated ▼ 11.3 years
- PRELIMINARY DESIGN Original anticipated ▼ 4.0 years
- PRELIMINARY DESIGN Current anticipated ▼ 11.0 years
- FINAL DESIGN Original anticipated ▼ 4.9 years
- FINAL DESIGN Current anticipated ▼ 10.5 years
- BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 5.4 years
- BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 10.3 years
- CONSTRUCTION TO 25% Original anticipated ▼ 6.1 years
- CONSTRUCTION TO 25% Current anticipated ▼ 9.6 years
- CONSTRUCTION TO 50% Original anticipated ▼ 6.8 years
- CONSTRUCTION TO 50% Current anticipated ▼ 8.9 years
- CONSTRUCTION TO 75% Original anticipated ▼ 7.4 years
- CONSTRUCTION TO 75% Current anticipated ▼ 8.3 years
- ORIGINAL EQUIP & FURNISHING Original anticipated ▼ 7.9 years
- ORIGINAL EQUIP & FURNISHING Current anticipated ▼ 8.0 years
- SUBSTANTIAL COMPLETION Original anticipated ▼ 8.2 years
- SUBSTANTIAL COMPLETION Current anticipated ▼ 7.8 years
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 8.4 years
-
10/12/2022
- DEVELOP SCOPE Original anticipated ▼ 3.3 years
- DEVELOP SCOPE Current anticipated ▼ 11.3 years
- PRELIMINARY DESIGN Original anticipated ▼ 4.0 years
- PRELIMINARY DESIGN Current anticipated ▼ 11.0 years
- FINAL DESIGN Original anticipated ▼ 4.9 years
- FINAL DESIGN Current anticipated ▼ 10.5 years
- BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 5.4 years
- BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 10.3 years
- CONSTRUCTION TO 25% Original anticipated ▼ 6.1 years
- CONSTRUCTION TO 25% Current anticipated ▼ 9.6 years
- CONSTRUCTION TO 50% Original anticipated ▼ 6.8 years
- CONSTRUCTION TO 50% Current anticipated ▼ 8.9 years
- CONSTRUCTION TO 75% Original anticipated ▼ 7.4 years
- CONSTRUCTION TO 75% Current anticipated ▼ 8.3 years
- ORIGINAL EQUIP & FURNISHING Original anticipated ▼ 7.9 years
- ORIGINAL EQUIP & FURNISHING Current anticipated ▼ 8.0 years
- SUBSTANTIAL COMPLETION Original anticipated ▼ 8.2 years
- SUBSTANTIAL COMPLETION Current anticipated ▼ 7.8 years
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 8.4 years
-
05/17/2022
- Current Budget decrease ▼ $75.0K
- DEVELOP SCOPE Original postponed ▲ 3.3 years
- DEVELOP SCOPE Current postponed ▲ 11.3 years
- PRELIMINARY DESIGN Original anticipated ▼ 4.0 years
- PRELIMINARY DESIGN Current anticipated ▼ 11.0 years
- FINAL DESIGN Original anticipated ▼ 4.9 years
- FINAL DESIGN Current anticipated ▼ 10.5 years
- BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 5.4 years
- BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 10.3 years
- CONSTRUCTION TO 25% Original anticipated ▼ 6.1 years
- CONSTRUCTION TO 25% Current anticipated ▼ 9.6 years
- CONSTRUCTION TO 50% Original anticipated ▼ 6.8 years
- CONSTRUCTION TO 50% Current anticipated ▼ 8.9 years
- CONSTRUCTION TO 75% Original anticipated ▼ 7.4 years
- CONSTRUCTION TO 75% Current anticipated ▼ 8.3 years
- ORIGINAL EQUIP & FURNISHING Original anticipated ▼ 7.9 years
- ORIGINAL EQUIP & FURNISHING Current anticipated ▼ 8.0 years
- SUBSTANTIAL COMPLETION Original anticipated ▼ 8.2 years
- SUBSTANTIAL COMPLETION Current anticipated ▼ 7.8 years
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 8.4 years
-
03/09/2022
- Original Start postponed ▲ 8.6 years
- Current Start postponed ▲ 4.9 years
- Original End anticipated ▼ 1.7 years
- Current End anticipated ▼ 5.8 years
- PUNCHLIST COMPLETE, JOB CLOSED Original postponed ▲ 8.4 years
- DEVELOP SCOPE Original anticipated ▼ 3.3 years
- DEVELOP SCOPE Current anticipated ▼ 11.3 years
- PRELIMINARY DESIGN Original anticipated ▼ 4.0 years
- PRELIMINARY DESIGN Current anticipated ▼ 11.0 years
- FINAL DESIGN Original anticipated ▼ 4.9 years
- FINAL DESIGN Current anticipated ▼ 10.5 years
- BID AWARD AND REGISTER CONTRCT Original anticipated ▼ 5.4 years
- BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 10.3 years
- CONSTRUCTION TO 25% Original anticipated ▼ 6.1 years
- CONSTRUCTION TO 25% Current anticipated ▼ 9.6 years
- CONSTRUCTION TO 50% Original anticipated ▼ 6.8 years
- CONSTRUCTION TO 50% Current anticipated ▼ 8.9 years
- CONSTRUCTION TO 75% Original anticipated ▼ 7.4 years
- CONSTRUCTION TO 75% Current anticipated ▼ 8.3 years
- ORIGINAL EQUIP & FURNISHING Original anticipated ▼ 7.9 years
- ORIGINAL EQUIP & FURNISHING Current anticipated ▼ 8.0 years
- SUBSTANTIAL COMPLETION Original anticipated ▼ 8.2 years
- SUBSTANTIAL COMPLETION Current anticipated ▼ 7.8 years
-
12/02/2021
- Current Budget decrease ▼ $1.20M
- Original Start anticipated ▼ 52.0 years
- Current Start anticipated ▼ 52.1 years
- Original End anticipated ▼ 52.9 years
- Current End anticipated ▼ 52.8 years
- DEVELOP SCOPE Original anticipated ▼ 4.1 months
- DEVELOP SCOPE Current anticipated ▼ 4.1 months
- FINAL DESIGN Original postponed ▲ 1.0 months
- FINAL DESIGN Current anticipated ▼ 6.1 months
- BID AWARD AND REGISTER CONTRCT Original postponed ▲ 7.1 months
- BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 3.1 months
- CONSTRUCTION TO 25% Original anticipated ▼ 1.0 months
- CONSTRUCTION TO 25% Current anticipated ▼ 7.1 months
- CONSTRUCTION TO 50% Original postponed ▲ 3.0 months
- CONSTRUCTION TO 50% Current postponed ▲ 30 days
- CONSTRUCTION TO 75% Original postponed ▲ 7.1 months
- CONSTRUCTION TO 75% Current anticipated ▼ 3.1 months
- ORIGINAL EQUIP & FURNISHING Original postponed ▲ 1.0 months
- SUBSTANTIAL COMPLETION Original anticipated ▼ 3.0 months
- SUBSTANTIAL COMPLETION Current postponed ▲ 2.0 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 5.1 months
-
08/05/2021
- Current Budget decrease ▼ $1.68M
- Original Start postponed ▲ 52.0 years
- Current Start postponed ▲ 52.1 years
- Original End postponed ▲ 52.9 years
- Current End postponed ▲ 52.8 years
-
01/14/2021
- Current Budget decrease ▼ $2.01M
- DEVELOP SCOPE Original anticipated ▼ 4.1 months
- DEVELOP SCOPE Current anticipated ▼ 4.1 months
- FINAL DESIGN Original postponed ▲ 1.0 months
- FINAL DESIGN Current anticipated ▼ 6.1 months
- BID AWARD AND REGISTER CONTRCT Original postponed ▲ 7.1 months
- BID AWARD AND REGISTER CONTRCT Current anticipated ▼ 3.1 months
- CONSTRUCTION TO 25% Original anticipated ▼ 1.0 months
- CONSTRUCTION TO 25% Current anticipated ▼ 7.1 months
- CONSTRUCTION TO 50% Original postponed ▲ 3.0 months
- CONSTRUCTION TO 50% Current postponed ▲ 30 days
- CONSTRUCTION TO 75% Original postponed ▲ 7.1 months
- CONSTRUCTION TO 75% Current anticipated ▼ 3.1 months
- ORIGINAL EQUIP & FURNISHING Original postponed ▲ 1.0 months
- SUBSTANTIAL COMPLETION Original anticipated ▼ 3.0 months
- SUBSTANTIAL COMPLETION Current postponed ▲ 2.0 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 5.1 months
-
11/23/2020
- DEVELOP SCOPE Original anticipated ▼ 4.1 months
- DEVELOP SCOPE Current anticipated ▼ 1.0 months
- PRELIMINARY DESIGN Current postponed ▲ 3.1 months
- FINAL DESIGN Original postponed ▲ 1.0 months
- FINAL DESIGN Current anticipated ▼ 3.1 months
- BID AWARD AND REGISTER CONTRCT Original postponed ▲ 7.1 months
- CONSTRUCTION TO 25% Original anticipated ▼ 1.0 months
- CONSTRUCTION TO 25% Current anticipated ▼ 4.0 months
- CONSTRUCTION TO 50% Original postponed ▲ 3.0 months
- CONSTRUCTION TO 50% Current postponed ▲ 4.1 months
- CONSTRUCTION TO 75% Original postponed ▲ 7.1 months
- ORIGINAL EQUIP & FURNISHING Original postponed ▲ 1.0 months
- ORIGINAL EQUIP & FURNISHING Current postponed ▲ 3.1 months
- SUBSTANTIAL COMPLETION Original anticipated ▼ 3.0 months
- SUBSTANTIAL COMPLETION Current postponed ▲ 5.1 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 5.1 months
-
04/16/2020
- ORIGINAL EQUIP & FURNISHING Original anticipated ▼ 1.0 months
- ORIGINAL EQUIP & FURNISHING Current anticipated ▼ 3.1 months
- PRELIMINARY DESIGN Current postponed ▲ 3.1 months
- FINAL DESIGN Original postponed ▲ 1.0 months
- FINAL DESIGN Current anticipated ▼ 3.1 months
- BID AWARD AND REGISTER CONTRCT Original postponed ▲ 7.1 months
- CONSTRUCTION TO 25% Original anticipated ▼ 1.0 months
- CONSTRUCTION TO 25% Current anticipated ▼ 4.0 months
- CONSTRUCTION TO 50% Original postponed ▲ 3.0 months
- CONSTRUCTION TO 50% Current postponed ▲ 4.1 months
- CONSTRUCTION TO 75% Original postponed ▲ 7.1 months
- SUBSTANTIAL COMPLETION Original anticipated ▼ 3.0 months
- SUBSTANTIAL COMPLETION Current postponed ▲ 5.1 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 5.1 months
- DEVELOP SCOPE Original postponed ▲ 4.1 months
- DEVELOP SCOPE Current postponed ▲ 1.0 months
-
01/16/2020
- PUNCHLIST COMPLETE, JOB CLOSED Original postponed ▲ 5.1 months
- DEVELOP SCOPE Original anticipated ▼ 4.1 months
- DEVELOP SCOPE Current anticipated ▼ 1.0 months
- PRELIMINARY DESIGN Current postponed ▲ 3.1 months
- FINAL DESIGN Original postponed ▲ 1.0 months
- FINAL DESIGN Current anticipated ▼ 3.1 months
- BID AWARD AND REGISTER CONTRCT Original postponed ▲ 7.1 months
- CONSTRUCTION TO 25% Original anticipated ▼ 1.0 months
- CONSTRUCTION TO 25% Current anticipated ▼ 4.0 months
- CONSTRUCTION TO 50% Original postponed ▲ 3.0 months
- CONSTRUCTION TO 50% Current postponed ▲ 4.1 months
- CONSTRUCTION TO 75% Original postponed ▲ 7.1 months
- ORIGINAL EQUIP & FURNISHING Original postponed ▲ 1.0 months
- ORIGINAL EQUIP & FURNISHING Current postponed ▲ 3.1 months
- SUBSTANTIAL COMPLETION Original anticipated ▼ 3.0 months
- SUBSTANTIAL COMPLETION Current postponed ▲ 5.1 months
-
10/25/2019
- PUNCHLIST COMPLETE, JOB CLOSED Original postponed ▲ 5.1 months
- DEVELOP SCOPE Original anticipated ▼ 4.1 months
- DEVELOP SCOPE Current anticipated ▼ 1.0 months
- PRELIMINARY DESIGN Current postponed ▲ 3.1 months
- FINAL DESIGN Original postponed ▲ 1.0 months
- FINAL DESIGN Current anticipated ▼ 3.1 months
- BID AWARD AND REGISTER CONTRCT Original postponed ▲ 7.1 months
- CONSTRUCTION TO 25% Original anticipated ▼ 1.0 months
- CONSTRUCTION TO 25% Current anticipated ▼ 4.0 months
- CONSTRUCTION TO 50% Original postponed ▲ 3.0 months
- CONSTRUCTION TO 50% Current postponed ▲ 4.1 months
- CONSTRUCTION TO 75% Original postponed ▲ 7.1 months
- ORIGINAL EQUIP & FURNISHING Original postponed ▲ 1.0 months
- ORIGINAL EQUIP & FURNISHING Current postponed ▲ 3.1 months
- SUBSTANTIAL COMPLETION Original anticipated ▼ 3.0 months
- SUBSTANTIAL COMPLETION Current postponed ▲ 5.1 months
-
04/25/2019
- Current End postponed ▲ 1.0 months
- DEVELOP SCOPE Original anticipated ▼ 4.1 months
- DEVELOP SCOPE Current anticipated ▼ 1.0 months
- PRELIMINARY DESIGN Current postponed ▲ 3.1 months
- FINAL DESIGN Original postponed ▲ 1.0 months
- FINAL DESIGN Current anticipated ▼ 3.1 months
- BID AWARD AND REGISTER CONTRCT Original postponed ▲ 7.1 months
- CONSTRUCTION TO 25% Original anticipated ▼ 1.0 months
- CONSTRUCTION TO 25% Current anticipated ▼ 4.0 months
- CONSTRUCTION TO 50% Original postponed ▲ 3.0 months
- CONSTRUCTION TO 50% Current postponed ▲ 4.1 months
- CONSTRUCTION TO 75% Original postponed ▲ 7.1 months
- ORIGINAL EQUIP & FURNISHING Original postponed ▲ 1.0 months
- ORIGINAL EQUIP & FURNISHING Current postponed ▲ 3.1 months
- SUBSTANTIAL COMPLETION Original anticipated ▼ 3.0 months
- SUBSTANTIAL COMPLETION Current postponed ▲ 5.1 months
- PUNCHLIST COMPLETE, JOB CLOSED Original anticipated ▼ 5.1 months