70 MULBERRY STREET - RECONSTRUCTION
Current Phase
Phase Start
Phase End
Min Date
Max Date
Managing Agency
Sponsor Agency
Budget Lines
Type Category
CCP Version
Forecasts
| Summary | Original | Current | Change (#) |
|---|---|---|---|
| Budget | |||
| Project Completion | |||
| Duration |
Agency Project Schedule
Project Schedule History
| Period | Current Phase | Completion Date Forecast | Variance (day) | Reason for Forecast Completion Change | Managing Agency Name | Data as of |
|---|
Budget & Spending
Planned
Adopted
Allocated
Commited
Spent
Checkbook
History
| Year-Month Reported | Total Budget | Budget Variance | Budget Variance % | Spend to Date | Spend to Date % |
|---|
Funding Source
| Fiscal Year | Total Budget (City + Non City) | City | Non City | Spend |
|---|
Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.
Change Log
-
09/2023
- Current Budget increase ▲ $135K
-
05/2024
- Current End postponed ▲ 6.0 months
- Current Duration increase ▲ 6.0 months
-
09/2024
- Current Budget increase ▲ $1.35M
- Current End postponed ▲ 3.0 months
- Current Duration increase ▲ 3.0 months
-
01/2025
- Current Budget increase ▲ $8.88M
- Current End postponed ▲ 3.5 months
- Current Duration increase ▲ 3.5 months