This dataset contains capital commitment plan data by project type, budget line and source of funds. The dollar values are in thousands. The dataset is updated three times a year during the Preliminary, Executive and Adopted Capital Commitment Plans.
Capital Project Detail Data - Dollars
BRUCKNER EXP / WESTCHESTER CREEK 1-066510 ()
Details
Publication Date
Summary | Original | Current | Change (#) |
---|---|---|---|
Budget | |||
Start | |||
End | |||
Duration |
Borough | |
---|---|
Managed By | |
Project Type | |
10-year Plan Category | |
Budget Lines | |
Community Districts Served | |
Explanation for Delay | |
Scope Summary | |
Site Description | |
City Prior Spending | |
Non City Prior Spending |
Milestones
* All numbers are in the chart are thousands.
Next 5 Years of Spending
* All numbers are in the chart are thousands.
Prior Spending
* All numbers are in the chart are thousands.
Budget Over Time
Additional Project Information
Description | Total City Planned Commit | Max Date | Min Date | Managing Agency Name |
---|
Commitments
Description | Date | Commitment Description | Commitment Type | Total Planned Commit |
---|
Our map uses data from Capital Projects Database (CPDB) - Projects (Polygons), Capital Projects Database (CPDB) - Projects (Points) datasets.
Change Log
-
05/24/2023
- Current Budget decrease ▼ $5.60M
- DEVELOP SCOPE Original anticipated ▼ 7.0 years
- DESIGN START Original anticipated ▼ 7.0 years
-
02/10/2023
- Current Budget decrease ▼ $2.06M
- CONSTRUCTION START Current postponed ▲ 54.7 years
- DESIGN START Original postponed ▲ 7.0 years
- DESIGN START Current postponed ▲ 46.6 years
- DEVELOP SCOPE Original postponed ▲ 7.0 years
- DEVELOP SCOPE Current postponed ▲ 44.5 years
-
10/12/2022
- CONSTRUCTION START Current postponed ▲ 54.7 years
- DEVELOP SCOPE Original anticipated ▼ 7.0 years
- DESIGN START Original anticipated ▼ 7.0 years
-
05/17/2022
- Current Budget decrease ▼ $4.81M
- CONSTRUCTION START Current postponed ▲ 54.7 years
- DEVELOP SCOPE Original anticipated ▼ 7.0 years
- DESIGN START Original anticipated ▼ 7.0 years
-
03/09/2022
- Current Budget decrease ▼ $4.12M
- Original End postponed ▲ 12.0 years
- Current End anticipated ▼ 2.0 years
- DEVELOP SCOPE Original anticipated ▼ 7.0 years
- DESIGN START Original anticipated ▼ 7.0 years
-
12/02/2021
- Current Budget decrease ▼ $6.07M
- Original Start anticipated ▼ 29.5 years
- Original End anticipated ▼ 52.4 years
- Current End anticipated ▼ 52.7 years
-
08/05/2021
- Current Budget increase ▲ $1.69M
- Original Start postponed ▲ 29.5 years
- Original End postponed ▲ 52.4 years
- Current End postponed ▲ 52.7 years
-
01/14/2021
- Current Budget decrease ▼ $2.05M
- Current Start anticipated ▼ 70.1 years
- CONSTRUCTION START Current postponed ▲ 52.7 years
-
11/23/2020
- Current Budget decrease ▼ $1.00K
- DEVELOP SCOPE Current anticipated ▼ 122.6 years
- DESIGN START Current anticipated ▼ 122.7 years
- CONSTRUCTION START Current anticipated ▼ 122.8 years
-
04/16/2020
- Current Budget increase ▲ $645K
- CONSTRUCTION START Current postponed ▲ 122.8 years
- DEVELOP SCOPE Current anticipated ▼ 122.6 years
- DESIGN START Current anticipated ▼ 122.7 years
-
01/16/2020
- Current Budget decrease ▼ $1.80M
- DEVELOP SCOPE Current anticipated ▼ 122.6 years
- DESIGN START Current anticipated ▼ 122.7 years
- CONSTRUCTION START Current anticipated ▼ 122.8 years
-
10/25/2019
- Current Budget decrease ▼ $1.00K
- Current End anticipated ▼ 3.1 months
- DEVELOP SCOPE Current anticipated ▼ 122.6 years
- DESIGN START Current anticipated ▼ 122.7 years
- CONSTRUCTION START Current anticipated ▼ 122.8 years
-
04/25/2019
- Current Budget decrease ▼ $297K
- DEVELOP SCOPE Current anticipated ▼ 122.5 years
- DESIGN START Current anticipated ▼ 122.5 years
- CONSTRUCTION START Current anticipated ▼ 122.5 years